Waste Management Licence Applications

South Africa’s core legislation on waste licensing is the National Environmental Management Waste Act, 2008 (Act No. 59 of 2008) (NEMWA). According to the NEMWA, no person may commence, undertake, or conduct a listed waste management activity unless a license is issued in respect of that activity.

  • If both NEMA listed activities and NEMWA waste management activities are triggered, an integrated EIA process must be followed.
  • Category A activities require a Basic Assessment process; Category B activities require a full scoping and EIA process; Category C activities need no licence but must conform to listed practices and standards.
  • An Environmental Assessment Practitioner is required, and the process takes between 8 and 14 months.
  • The maximum fine for not applying for a WML is R10 000 000 and / or 10 years imprisonment.

When is a Waste Management Licence required?

An integrated environmental authorization process has been established with the NEMA and NEMWA which means that if both NEMA listed activities and NEMWA waste management activities are triggered, an integrated EIA process must be followed.

NEMWA lists several waste activities in three separate lists. Category A activities require a Basic Assessment process and Category B listed activities require a full scoping and EIA process. These activities include, but are not limited to:

  • Waste storage
  • Processing of waste e.g., sorting, shredding, grinding and bailing
  • Re-use and recycling
  • Recovery of waste, incl. refining, utilisation and co-processing
  • Treatment
  • Disposal to land

Note: Category C listed activities do not need a licence, however, they must conform to certain practices and standards listed.

The assessment

If you trigger a listed activity, you will be required to apply for a Waste Management Licence. The assessment will ensure that the facility does not negatively impact the environment. Furthermore, an Environmental Assessment Practitioner is required to conduct the assessment. The process will take between 8 and 14 months to complete. The maximum fine of not applying for a WML is R10 000 000 and / or 10 years imprisonment.