| Site visit and baseline assessment | Step 1: Undertake a site visit with the client to determine the baseline conditions of the site. Undertake a brief baseline screening using GIS Systems. | First week of appointment (dependent on availability) |
|---|
| Pre-application process | Step 2: Submission of enquiry form and/or pre-application meeting with the competent authority (CA) | 1 week (dependent on availability) |
|---|
| Public participation – phase 1 | Step 3: Commence with the Public Participation Process (this includes the notification of I&APs, adjacent neighbours, placement of signboards, advertisements, BID) | Allocate 21 days for I&APs to register |
|---|
| Specialist studies | Step 4: In accordance with the requirements laid out by the competent authority – specialists will be appointed to undertake the required studies | Allow 6 – 8 weeks for completion |
|---|
| Scoping phase 1 | Step 5: Compilation of the draft scoping report including the baseline assessment undertaken in step 1 | 2 weeks – if information is received timeously |
|---|
| Administration | Step 6: Submission of application forms to the competent authority (CA) | Allow 2 weeks for acceptance. |
|---|
| Public participation – phase 2 | Step 6: Submission of the Scoping Report for commenting period | Allocate 30 days for I&APs to comment |
|---|
| Scoping phase 2 | Step 7: Finalisation of scoping report inclusive of comments received. Step 8: Submission of final scoping report to the competent authority (CA) | The CA has 43 days to accept or reject the Scoping Report. |
|---|
| Environmental impact reporting and assessment | Step 9: Compilation of the draft environmental impact report (EIR) and draft environmental management programme (EMPr) | 2 weeks – if information is received timeously |
|---|
| Public participation – phase 3 | Step 10: Submission of the draft environmental impact report (EIR) and draft environmental management programme (EMPr) for commenting period | Allocate 30 days for I&APs to comment |
|---|
| Finalisation | Step 11: Collation of comments and responses and finalisation of draft reports. | 1 – 2 weeks (provided no major changes) |
|---|
| Administration and submission | Step 12: Submission of Final EIR and EMPr to the competent authority (CA) | Allow 14 days for acknowledgement |
|---|
| Acceptance / rejection and appeals | Step 13: Issuing of the environmental authorization. Step 14: Issuing of the mining permit. Step 15: Notification of I&APs of decision. Step 16: Handling of appeals | CA has 107 days to accept/reject the final BAR. Appeals may take up to 3 months. |
|---|
| Licence / right | Step 17: Submission of application to relevant authority for the approval of licenses / rights. | May take up to 3 months. |
|---|