Blog

WASTE MANAGEMENT LICENSE (WML)

South Africa’s core legislation on waste licensing is the National Environmental Management Waste Act, 2008 (Act No. 59 of 2008) (NEMWA). According to the NEMWA, no person may commence, undertake, or conduct a waste management activity listed in this schedule unless a license is issued in respect of that activity. Additionally, an integrated environmental authorization process has been established with the NEMA and NEMWA which means that if both NEMA listed activities and NEMWA waste management activities are triggered, an integrated EIA process must be followed.

NEMWA lists several waste activities in three separate lists. Category A activities requires Basic Assessment process and Category B listed activities requires a full scoping and EIA process. These activities include, but are not limited to,

•Waste Storage

•Processing of waste e.g., sorting, shredding, grinding and bailing,

•Re-use and recycling,

•Recovery of waste, incl. refining, utilisation and co-processing,

•Treatment,

•Disposal to land.

*Category C listed activities do not need a licence, however, it must conform to certain practices and standards listed.

If you trigger a listed activity, you will be required to apply for a Waste Management Licence. – The assessment will ensure that the facility does not negatively impact the environment. Furthermore, an Environmental Assessment Practitioner is required to conduct the assessment. The process will take between 8 and 14 months to complete.  The maximum fine of not applying for a WML is R10 000 000 and / or 10 Years imprisonment.

Steps to be followed:

BASIC ASSESSMENT AND WASTE MANAGEMENT LICENSE
ProcessStepsTimeframes
SCREENING PROCESSStep 1: Submission of enquiry form and/or pre-application meeting with the competent authority (CA)Weeks 1 – 2 (Dependent on availability
SPECIALIST STUDIESStep 2: In accordance with the requirements laid out by the competent authority – specialists will be appointed to undertake the required studiesAllow 6 – 8 weeks for completion
PUBLIC PARTICIPATION – PHASE 1Step 3: Commence with the Public Participation Process (this includes the notification of I&APs, adjacent neighbours, placement of signboards, advertisements, BID)Allocate 21 days for I&APs to register
INTEGRATION AND ASSESSMENTStep 4: Compilation of the draft basic assessment report (BAR) and the draft EMPr.2 weeks – if information is received timeously
PUBLIC PARTICIPATION – PHASE 2Step 5: Submission of the Draft Basic Assessment Report for commenting periodAllocate 30 days for I&APs to comment
FINALISATIONStep 6: Collation of comments and responses and finalisation of draft reports1 – 2 weeks (provided no major changes)
ADMINISTRATION AND SUBMISSIONStep 7: Submission of Final Basic Assessment Report to the competent authority (CA)Allow 14 days for acknowledgement
ACCEPTANCE/ REJECTION AND APPEALSStep 8: Issuing of the environmental authorization
Step 9: Notification of I&APs of decision
Step 10: Handling of appeals
CA has 107 days to accept/reject the final BAR. Appeals may take up to 3 months.
ENVIRONMENTAL IMPACT ASSESSMENT AND WASTE MANAGEMENT LICENSE
ProcessStepsTimeframes
SITE VISIT AND BASELINE ASSESSMENTStep 1: Undertake a site visit with the clientto determine the baseline conditions of the site. Undertake a brief baseline screening using GIS Systems.First Week of appointment (Dependent on availability)
PRE-APPLICATION PROCESSStep 2: Submission of enquiry form and/or pre-application meeting with the competent authority (CA)1 week (Dependent on availability)
PUBLIC PARTICIPATION – PHASE 1Step 3: Commence with the Public Participation Process (this includes the notification of I&APs, adjacent neighbours, placement of signboards, advertisements, BID)Allocate 21 days for I&APs to register
SPECIALIST STUDIESStep 4: In accordance with the requirements laid out by the competent authority – specialists will be appointed to undertake the required studiesAllow 6 – 8 weeks for completion
SCOPING PHASE 1Step 5: Compilation of the draft scoping report including the baseline assessment undertaken in step 12 weeks – if information is received timeously
ADMINISTRATIONStep 6: Submission of application forms to the competent authority (CA)Allow 2 weeks for acceptance.
PUBLIC PARTICIPATION PHASE 2Step 7: Submission of the Scoping Report for commenting periodAllocate 30 days for I&APs to comment
SCOPING PHASE 2Step 8: Finalisation of scoping report inclusive of comments received.
Step 9: Submission of final scoping report to the competent authority (CA)
The CA has 43 days to accept or reject the Scoping Report.
ENVIRONMENTAL IMPACT REPORTING AND ASSESSMENTStep 10: compilation of the draft environmental impact report (EIR) and draft environmental management Programme (EMPr)2 weeks – if information is received timeously
PUBLIC PARTICIPATION PHASE 3Step 11: Submission of the draft environmental impact report (EIR) and draft environmental management Programme (EMPr) for commenting periodAllocate 30 days for I&APs to comment
FINALISATIONStep 12: Collation of comments and responses and finalisation of draft reports.1 – 2 weeks (provided no major changes)
ADMINISTRATION AND SUBMISSIONStep 13: Submission of Final EIR and EMPr to the competent authority (CA)Allow 14 days for acknowledgement
ACCEPTANCE/ REJECTION AND APPEALSStep 14: Issuing of the environmental authorization
Step 15: Issuing of the mining permit
Step 16: Notification of I&APs of decision
Step 17: Handling of appeals
CA has 107 days to accept/reject the final BAR. Appeals may take up to 3 months.
LICENSE / RIGHTStep 18: Submission of application to relevant authority for the approval of licenses / rights.May take up to 3 months.

Leave a Reply

Your email address will not be published. Required fields are marked *